Business License Application Procedure

Online submission with attached documents

Application review and file opening

Fee payment

Referral to approving authorities

If the application is not approved, corrections must be made and resubmitted to the approving authorities

Business License

Fee

The price payable for the license application is updated according to the Ministry of Finance index. The binding rate is that calculated by the Business Licensing Department on the day the charge is generated. Please note, the calculation is per item separately, in accordance with the Business Licensing Order.

Timetables

To streamline and expedite the licensing process and improve service to the public, the Minister of the Interior imposed time limits on licensing authorities and approving bodies for handling an application for a license / temporary permit or for a preliminary opinion, so that all licensing and approving bodies are required to respond to all inquiries within a set time as detailed in the timelines below (further details regarding timetables can be obtained from the local authority):

Timeline for Application and License Issuance

Subject Local Authority Processing Approving Bodies Processing Local Processing for License Issuance Total for Process
Minimum Time 21 days 30 days 7 days About two months
Maximum Time 45 days 90 days 7 days About six months

Timeline for License Renewal

Processing Entity Local Authority Approving Bodies Local Authority
Action The licensing authority notifies the approving bodies Approving bodies respond to the local authority Notice to periodic/temporary license holder regarding license issuance (requires holder declaration and fee payment) or rejection of application
Time 60 days prior to license expiration 90 days prior to license expiration 14 days prior to license expiration

Note:
These times are based on the premise that the applicant complies with all legal requirements and there is no delay on the applicant's part.
A delay on the part of the applicant will extend the processing time and the timeline will change accordingly.

To view and check the status of your business license application - click here

Groups of Businesses Requiring a License

The Minister of the Interior, after consulting with the Ministers of Environmental Protection, Public Security, Labor, Agriculture, and Health – categorized in the Business Licensing Order (Businesses Requiring Licensing) 5755 - 1995 ten primary groups, with each group containing a list of items designated as requiring a license.

Group 1 - Health, Pharmacy, and Cosmetics.
Group 2 - Fuel and Energy.
Group 3 - Agriculture and Animals.
Group 4 - Food.
Group 5 - Water and Waste.
Group 6 - Commerce and Miscellaneous.
Group 7 - Public Entertainment, Recreation, and Sports.
Group 8 - Vehicles and Transportation.
Group 9 - Guard and Security Services.
Group 10 - Industry, Crafts, Chemistry, and Minerals.

Objection (Appeal)

Under the reform in the Business Licensing Law, an applicant or business owner is entitled to submit an objection, which is essentially an appeal against a refusal to grant a license, temporary permit, or expedited permit, or against conditions or documents required of them.

How to Submit an Objection

  1. The objection must be submitted using the Objection Form to Miki Menachem – For the objection form click here
    Miki Menachem
    Director of Operations and Environment Department
  2. Proof of fee payment must be attached
  3. The objection must be submitted in duplicate.
  4. To each copy of the objection, attach the license / temporary permit / expedited permit or application to obtain them, and the requirement or decision against which the objection is filed.
  5. Attach any additional relevant document
  6. Detail in the objection form the entity to whom the objection is submitted, the requirement or decision subject to the objection; date of receipt; grounds for the objection, and the objector's alternative proposals to the requirement, if any.
  7. An objector seeking to suspend the validity of the requirement or decision pending a determination on the objection shall attach a reasoned request in this regard.

The Objection Shall Be Submitted in Three Copies

  • Two copies to the national authorized body on whose behalf the requirement or decision was issued or which is tasked by law with fulfilling that purpose.
  • The objector shall submit an additional copy of the objection to the licensing authority (in the event the objection is not submitted directly to the licensing authority).

If the objection includes a claim of incompatibility with a requirement established on behalf of another approving body or for fulfilling a purpose it is entrusted with, an additional copy of the objection must be submitted to the national authorized body on behalf of the other approving body. The licensing authority is not authorized to accept objections against requirements or decisions of approving bodies. The objection must be addressed to the relevant approving body.

An objection must be filed within 30 days of receiving the decision or requirement after payment.

Timeframe for Determining an Objection

The national authorized body must decide on the application within 30 days of its submission.

  • A national authorized body may, in a reasoned decision, extend the time for deciding on the application by an additional 30 days. In the event that a national authorized body (on behalf of the approving body) considers that the objection justifies a change in the uniform specification, it may extend the deadline for issuing a decision on the objection by 90 days.
  • The authorized body shall notify the objector and the licensing authority accordingly, noting that the possibility of amending the uniform specification is being examined. If the objection concerns an alleged incompatibility between the requirements of two approving bodies, a national authorized body may, in a reasoned decision, extend the time for determining the objection by 120 days.

Objections concerning incompatibility between requirements of the licensing authority and an approving body: An objection asserting incompatibility between a requirement of an approving body and a requirement of the licensing authority shall be determined by a national authorized body within the ministry of the approving body, after hearing the arguments of the licensing authority regarding the disputed matter. In the reasoning of its decision, the national authorized body shall address the arguments of the licensing authority.